Tamarack Sno-Park will be having some ongoing construction over the next month or so. Please plan accordingly!

Tamarack Sno-Park to Undergo Construction Activities

MOUNTAIN COMMUNITIES – The Tamarack Sno-Park on the High Sierra Ranger District will be undergoing construction activities July 6 – Aug. 11.

See map and schedule below. 

Image of Avison Construction logo. July 6: Avison Construction will be grinding/pulverizing asphalt at the parking lot. Traffic will be stopped and allowed to pass through periodically during this operation.

July 7 – 11:  Grading and compacting of the subgrade will take place, traffic will be allowed to pass thru periodically during this operation.

July 12 – 13: The contractor will be paving and there will be a hard closure on July 12th. NO traffic allowed. On July 13th there will be delayed traffic.

Image of an Avison Construction truck. July 22 – 25: Sign installation, no traffic delays expected.

July 26 – Aug. 11: Restroom painting. Buildings will be closed during this time for maintenance.

Aug. 12: Parking lot striping. Traffic will be allowed to pass thru periodically during this operation

For more information, please contact the High Sierra Ranger District at 559-855-5355.